Gas Supply Headroom

Pass — 192.2 MW net at VICTORIA INVST M4400 MP 200.1 (TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC, 5.59 mi)
Criteria: Incremental uncontracted gas headroom ≥ 50 MW net continuous power (BTM50-US-V3:GSH). Point-level arithmetic screen at reference 8,000 Btu/kWh net HHV heat rate.
Geoforge curated dataset
Gas Supply Headroom
192.2 MW net
At VICTORIA INVST M4400 MP 200.1 (5.6 mi)
Best Delivery Point
VICTORIA INVST M4400 MP 200.1
TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC · 5.6 mi from site
Available Capacity
36,894 Dth/day
AVAILCAP = MAXCAP (66,894) − SCHEDCAP (30,000)
Points in Radius
13 7 ≥ 50 MW
5 delivery · 8 receipt · 7 operators
Reference Heat Rate
8,000 Btu/kWh
Net HHV · Assumed (not project-supported)
Evidence Basis
POSTED_OAC_SCREEN
Point-level only · No path-to-meter engineering

Summary

Gas Delivery & Receipt Points (25-mile radius)

Rank Name Operator Type Dist (mi) MAXCAP AVAILCAP MW Net Status
1 VICTORIA INVST M4400 MP 200.1 TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC Delivery 5.6 66,894 36,894 192.2 Pass
2 GCENGY/TGP COLETO CREEK VICTORIA TENNESSEE GAS PIPELINE Receipt 7.8 3,734 3,494 18.2 Fail
3 GBRA #1 - ALEGRE ENERGY TRUNKLINE GAS COMPANY, LLC Receipt 8.7 1,000 900 4.7 Fail
4 021032 - DISCOVERY-T KINETICA PARTNERS LLC Delivery 8.8 290,000 7,455 38.8 Fail
5 TELFERNER FIELD - WEST TRUNKLINE GAS COMPANY, LLC Receipt 13.5 15,000 14,735 76.7 Pass
6 TRANSCO-GULFSTREAM CODEN FLORIDA GAS TRANSMISSION Delivery 14.4 — 97,142 505.9 Pass
7 TENN CARNES (DEL) FLORIDA GAS TRANSMISSION Delivery 15.0 69,000 45,000 234.4 Pass
8 TERRELL POINT FIELD - RINCON PETROLEUM TRUNKLINE GAS COMPANY, LLC Receipt 16.4 5,000 4,914 25.6 Fail
9 TURKEY CREEK - PETROLEUM FUELS TRUNKLINE GAS COMPANY, LLC Receipt 16.4 15,000 14,100 73.4 Pass
10 T2 GAS / NGPL REFUGIO NATURAL GAS PIPELINE (KINDER MORGAN) Receipt 18.2 300,000 285,000 1484.4 Pass
11 MUSTANG FUEL CORP-KEERAN #2 FLORIDA GAS TRANSMISSION Receipt 19.3 6,600 390 2.0 Fail
12 AUBURN ENTERPRISES - KERLICK #1, DEWITT, TX TEXAS EASTERN TRANSMISSION Receipt 20.5 10,438 10,372 54.0 Pass
13 PALATKA GAS-PALATKA FLORIDA GAS TRANSMISSION Delivery 21.1 6,500 5,600 29.2 Fail
This is a point-level arithmetic screen using HIFLD/Platts AVAILCAP data at a reference 8,000 Btu/kWh heat rate. It is NOT a path-to-meter deliverability assessment. FERC IOC contract allocation, hourly flow caps, inlet pressure, gas quality, and engineering path confirmation are not available in this dataset. Receipt points may not serve as delivery taps for new industrial load.

Analysis

VICTORIA INVST M4400 MP 200.1 (TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC, 5.59 mi) reports 36,894 Dth/day available capacity, equivalent to 192.2 MW net at an assumed 8,000 Btu/kWh heat rate — above the 50 MW threshold. 7 of 13 inventoried points within 25 mi exceed 50 MW equivalent. This is a point-level arithmetic screen using posted AVAILCAP data, not a path-to-meter deliverability assessment; hourly flow limits, pressure, engineering path, and service terms remain unconfirmed.

The site is located in Victoria County, TX, within the Gulf Coast gas transmission corridor. Seven distinct pipeline operators serve the 25-mile radius: Transcontinental Gas Pipe Line (Transco), Tennessee Gas Pipeline, Florida Gas Transmission, Trunkline Gas Company, Natural Gas Pipeline of America (Kinder Morgan), Kinetica Partners, and Texas Eastern Transmission. The nearest delivery point — VICTORIA INVST M4400 MP 200.1 on Transco's system — reports 66,894 Dth/day design capacity with 36,894 Dth/day available (AVAILCAP), equivalent to 192.2 MW net at the reference heat rate.

Per the BTM50-US-V3:GSH methodology, several decision gates remain unresolved from available data: GSH_SERVICE (no hourly/seasonal flow or pressure data), GSH_ENGINEERING (no lateral/meter path confirmation), and GSH_HEAT_RATE (assumed, not project-supported). The AVAILCAP figure is an undated Platts snapshot; current operator postings should be verified. This screening result is conditional on confirming the delivery path, pressure, and service terms with the pipeline operator.

Next Steps

Measurement: WGS 84 / UTM zone 14N (EPSG:32614), utm