| Project Name | Voltage | Status | In-Service | Owner | Route | Miles | Tier |
|---|---|---|---|---|---|---|---|
| 69 kV | Planned | 2029 | STEC | San Diego → Orange | 21.6 | Tier 4 | |
| 138 kV | Planned | 2027 | CNP | West Columbia → Damon | 6.6 | Tier 4 | |
| 138 kV | Planned | 2028 | CNP | West Columbia → Needville | 13.8 | Tier 3 | |
| 345 kV ⚠️ | Planned | 2026 | CNP | STP → Hillje | — | Tier 4 | |
| 345 kV ⚠️ | Planned | 2029 | CNP | STP → Hillje | — | Tier 4 | |
| 345 kV ⚠️ | Under Construction | 2025 | AEP TCC | Angstrom → STP | — | Tier 4 | |
| 345 kV ⚠️ | Planned | 2025 | AEP TCC | Angstrom → STP | — | Tier 4 |
ERCOT TPIT shows 7 planned transmission upgrades within 25 miles of the site, spanning 2x 138 kV, 4x 345 kV, 1x 69 kV. All projects are in the Near (2025-2029) horizon. Four 345 kV upgrades are flagged as major, including FRM2 upgrades at STP-Hillje and the Charger Solar/Angstrom-STP interconnections. Capacity impact data is not available in the ERCOT TPIT dataset.
The site falls within ERCOT’s jurisdiction, which maintains a published Regional Transmission Plan (RTP) and tracks projects through the Transmission Project Information Tracking (TPIT) system. Seven planned upgrades intersect the 25-mile search radius, spanning 69 kV to 345 kV voltage classes. All seven projects are in the near-term planning horizon (2025–2029).
Four of the seven upgrades operate at 345 kV and are flagged as major upgrades per the methodology (345 kV+). These include two Facility Ratings Methodology Phase 2 (FRM2) upgrades on the STP–Hillje 345 kV corridor, the Charger Solar Interconnection (under construction, 2025), and the Angstrom–STP 345 kV line MOT increase. The remaining upgrades include two 138 kV reconductoring/rebuild projects on the West Columbia–Damon–Needville corridor by CenterPoint Energy, and a 69 kV upgrade by STEC on the San Diego–Orange Grove segment.