Adjacent Transmission Lines

Tier 2 — 4 lines ≥138 kV within 5 mi
Criteria: Count of transmission lines ≥138 kV within 5 miles of site boundary. Zones: Tier 1 ≥5 lines; Tier 2 = 3–4; Tier 3 = 1–2; Fail = 0. Promotion: any 345+ kV line within 1 mi → Tier 1.
Source: Geoforge grid dataset · US Transmission Lines · 2026-06-16
Site Assessment
✓ Tier 2
4 lines ≥138 kV within 5 mi of parcel boundary
Lines ≥138 kV
4 within 5 mi
Closest: ALLENHURST to CANEY at 2.83 mi
Total Lines (≥69 kV)
8
4 at 138 kV · 4 at 69 kV
Total Mileage in Buffer
23.3 mi
Combined transmission line length within 5-mi radius
Highest Voltage
138 kV
138 kV class · AEP TEXAS CENTRAL COMPANY
On-Parcel Crossings
0
No lines cross the parcel boundary

Summary

Transmission Lines Within 5-Mile Buffer (8 lines ≥69 kV)

Voltage Owner/TSP Line Name Sub 1 Sub 2 Dist (mi) Length (mi) On Parcel Cap (MW)
138 kV AEP TEXAS CENTRAL COMPANY ALLENHURST to CANEY ALLENHURST CANEY 2.8 2.0 No 300
138 kV Unknown N/A N/A Tenaris Substation 3.6 0.2 No
138 kV AEP TEXAS CENTRAL COMPANY VAN VLECK to ALLENHURST VAN VLECK ALLENHURST 4.0 1.8 No 300
138 kV Unknown ALLENHURST to ALLENHURST ALLENHURST ALLENHURST 4.4 0.7 No
69 kV AEP Texas Franklins Camp to CANEY Franklins Camp CANEY 0.9 10.3 No 83
69 kV AEP Texas CANEY to WEEDHAVEN CANEY WEEDHAVEN 2.9 2.8 No
69 kV AEP Texas CANEY to WEEDHAVEN CANEY WEEDHAVEN 2.9 2.8 No
69 kV AEP Texas CANEY to WEEDHAVEN CANEY WEEDHAVEN 2.9 2.8 No 83

Analysis

The the site has 4 transmission lines rated at 138 kV or above within 5 miles of the parcel boundary, plus 4 additional lines at 69 kV. The total transmission line mileage within the 5-mile buffer is 23.3 miles, indicating moderate grid density in the area. The closest 138 kV line (ALLENHURST to CANEY) is 2.83 miles from the parcel boundary, operated by AEP TEXAS CENTRAL COMPANY. No transmission lines cross the parcel boundary directly. The highest voltage class present within 5 miles is 138 kV. All identified lines are AEP Texas or AEP Texas Central Company infrastructure, indicating a single utility service territory which simplifies interconnection negotiations.

Next Steps

  • Contact AEP Texas Central Company to discuss interconnection options at the ALLENHURST or CANEY substations, which are endpoints of the nearby 138 kV lines.
  • Request a feasibility study for a gen-tie connection to the nearest 138 kV line (ALLENHURST to CANEY corridor, 2.8 mi from parcel).
  • Evaluate whether the 69 kV Franklins Camp-CANEY line (0.9 mi from parcel) could serve as a temporary or supplementary interconnection point for lower-capacity needs.
  • Investigate potential for higher-voltage (345 kV) transmission access — the nearest 345 kV lines are approximately 8-10 miles away near the South Texas Project area.

Sources