Delivery (11-23 mo) absorbed into construction (parallel)
| COMPONENT | LOW (MO) | HIGH (MO) |
|---|---|---|
| Component 1 — POI-side construction | 24 | 36 |
| Component 1b — Site-to-POI delivery path Parallel with Component 1; POI-side construction is critical |
11 | 23 |
| Component 2 — ERCOT study process | 6 | 12 |
| Component 3 — CCN/CPCN permitting | 0 | 0 |
| Effective construction (parallel) Critical: POI-side construction |
24 | 36 |
| Total | 30 | 48 |
| Base midpoint | 39 months | |
| Final adjusted midpoint | 39 months | |
| NAME | kV | YEAR | WORST MW | BEST MW | DIST (MI) |
|---|---|---|---|---|---|
| LINNVILLE | 138 | 2025 | 308 | 308 | 7.6 |
| PLEDGER | 138 | 2025 | 530 | 530 | 14.3 |
| Gulf Star | 138 | 2025 | 448 | 448 | 15.8 |
| NEW GULF | 138 | 2025 | 406 | 406 | 17.2 |
| REFUGE | 345 | 2026 | 342 | 342 | 8.7 |
| HAWKINS POI | 345 | 2028 | 312 | 312 | 8.2 |
| SWEENY | 138 | 2029 | 283 | 283 | 9.9 |
| West Columbia Main | 230 | 2029 | 283 | 283 | 15.5 |
LINNVILLE (138 kV) is the selected Point of Interconnection (POI), located 7.6 miles from the site boundary in BRAZORIA County, Texas. The substation demonstrates worst-case offtake capacity of 308 MW (capacity from the 2025 study year), exceeding the 250 MW target load.
The estimated time-to-power range is 30–48 months (midpoint 39 months), placing the site in the Extended zone. The binding constraint is poi-side construction. ERCOT interconnection study processes (6–12 months) run sequentially with construction. Texas exempts existing-substation modifications from CCN permitting requirements, eliminating a potential 6–18 month regulatory delay.
Eight substations within the 25-mile search radius meet the 250 MW worst-case offtake threshold in at least one study year. The delivery path from the site to LINNVILLE (7.6 miles at 138 kV) is absorbed into the POI-side construction timeline under the parallelism rule, as POI-side construction is the longer track.
Measurement: WGS 84 / UTM zone 15N (EPSG:32615), utm