Time-to-Power Inputs

Extended — 30–48 mo (mid 39 mo) · LINNVILLE 138kV
Criteria: Estimated time to energize a 250 MW hyperscale load via the highest-ranked substation POI. Thresholds: ≤24 mo (Fast Track), ≤36 mo (Feasible), ≤60 mo (Extended), >60 mo (Not Viable). Lower is better.
Geoforge curated dataset · 2026-08-17
TIME-TO-POWER RANGE
30–48 months
Midpoint: 39 months
SELECTED POI
LINNVILLE 138 kV
7.6 mi from site boundary
OFFTAKE CAPACITY AT POI
308–308 MW Meets 250 MW
capacity from the 2025 study year
BINDING CONSTRAINT
POI-side construction
Delivery path absorbed into POI construction timeline
ISO / PERMITTING
ERCOT CCN Exempt
Matagorda County, Texas
SUBSTATIONS MEETING TARGET
8 of 61
Curated substations within 25 mi meeting 250 MW worst-case

Offtake Capacity Envelope — LINNVILLE

Timeline Breakdown (months)

Delivery (11-23 mo) absorbed into construction (parallel)

Summary

Timeline Breakdown

COMPONENT LOW (MO) HIGH (MO)
Component 1 — POI-side construction 24 36
Component 1b — Site-to-POI delivery path
Parallel with Component 1; POI-side construction is critical
11 23
Component 2 — ERCOT study process 6 12
Component 3 — CCN/CPCN permitting 0 0
Effective construction (parallel)
Critical: POI-side construction
24 36
Total 30 48
Base midpoint 39 months
Final adjusted midpoint 39 months

Substations Meeting 250 MW Target

NAME kV YEAR WORST MW BEST MW DIST (MI)
LINNVILLE 138 2025 308 308 7.6
PLEDGER 138 2025 530 530 14.3
Gulf Star 138 2025 448 448 15.8
NEW GULF 138 2025 406 406 17.2
REFUGE 345 2026 342 342 8.7
HAWKINS POI 345 2028 312 312 8.2
SWEENY 138 2029 283 283 9.9
West Columbia Main 230 2029 283 283 15.5

Analysis

LINNVILLE (138 kV) is the selected Point of Interconnection (POI), located 7.6 miles from the site boundary in BRAZORIA County, Texas. The substation demonstrates worst-case offtake capacity of 308 MW (capacity from the 2025 study year), exceeding the 250 MW target load.

The estimated time-to-power range is 30–48 months (midpoint 39 months), placing the site in the Extended zone. The binding constraint is poi-side construction. ERCOT interconnection study processes (6–12 months) run sequentially with construction. Texas exempts existing-substation modifications from CCN permitting requirements, eliminating a potential 6–18 month regulatory delay.

Eight substations within the 25-mile search radius meet the 250 MW worst-case offtake threshold in at least one study year. The delivery path from the site to LINNVILLE (7.6 miles at 138 kV) is absorbed into the POI-side construction timeline under the parallelism rule, as POI-side construction is the longer track.

Key Risks

Next Steps

Measurement: WGS 84 / UTM zone 15N (EPSG:32615), utm

Sources